Demo with made-up jobs and people. Buttons that save, send or ask the AI are switched off here; in the real app they run on the owner's Mac. Back to the portfolio
Reclaimed Space Crafters Next task
1001-ALV Dana Alvarez Stage 4 of 5: Do the work, get paid Call 555-0100Email Dana
  1. ✓Write the estimate
  2. ✓Send it
  3. ✓Get it signed
  4. 4Do the work, get paid
  5. 5Wrap up
Next: Waiting on payment 1001-ALV-3Nothing to press until then. $3,360 invoiced. When it arrives, the email check suggests it for approval.
Job

1001-ALV · Dana Alvarez

In Progress
Contract
$35,450.00
Paid
$24,470.00
Still owed
$10,980.00
Expenses
$7,371.64
Profit so far
$28,078.36
Client details and dates
Every step on this job
✓ Estimate written · ○ Price checked · ✓ Estimate sent · ✓ Contract signed · ✓ First payment invoiced · ✓ First payment paid · ✓ Receipts and hours logged · ○ Final payment paid

Estimate & contract Change orders Room model Safety assessment Crew brief Progress Client update

Crew hours · 144 hours · about $4,680.80 in labor

2026-10-20Morgan Shaw8 h
2026-10-20Chris Lee8 h
2026-10-20Pat Rivera8 h
2026-10-19Morgan Shaw8 h
2026-10-19Chris Lee8 h
2026-10-19Pat Rivera8 h
2026-10-18Morgan Shaw8 h
2026-10-18Chris Lee8 h

All hours and the crew

Payment schedule · adds up to the contract

Payment ID (QB invoice #)What it's forAmountInvoice sentDate paidAmount paid
1001-ALV-1
Schedule hold + all materials + 20% of labor
At acceptance of the estimate
$21,110.00
1001-ALV-2
20% of labor: Phases 1–2
Upon completion of Phases 1–2, Steps 1–4
$3,360.00
1001-ALV-3
Invoiced
20% of labor: Phases 3–4
Upon completion of Phases 3–4, Steps 5–8
$3,360.00
1001-ALV-4
Not yet
20% of labor: Phase 5
Upon completion of Phase 5, Steps 9–10
$3,360.00
1001-ALV-5
Not yet
20% of labor: Phase 6 + debris / dump fee
Upon completion of Phase 6, Steps 11–12
$4,260.00
Add payment 1001-ALV-6

Change order? Add it here as the next payment and raise the contract total above.

Expenses on this job

DateVendorWhatCategoryAmountFrom
2026-10-18Home DepotUnder-cabinet lights and wireMaterials $186.20manual
2026-10-13Cabinet supplierCabinet depositMaterials $4,875.00manual
2026-10-09Lumber yardBeam, posts and framing lumberMaterials $2,310.44manual