Crew brief · 1001-ALV
Dana Alvarez · 14 Sample Lane, Saratoga Springs, NY · 555-0100
Kitchen · 4-5 weeks on site, Monday-Friday. · Crew: 1 general contractor, 1 carpenter, 1 helper part-time · about 450 crew-hours
Remove the wall between kitchen and dining room, add a beam, new cabinets, butcher-block counters and open shelves.
Before you start
- First payment received and materials ordered. Call Nick if not.
- Photos of the work area before you touch anything.
- Any subcontractor on site has a current insurance certificate.
- Daily: who worked and how many hours goes into the Crew tab.
Work, step by step
PHASE 1: LAYOUT AND ORDERING
☐ 1. Measure and confirm the cabinet layout.
☐ 2. Order cabinets and counters.
PHASE 2: PROTECTION AND DEMOLITION
☐ 3. Protect floors and doorways.
☐ 4. Remove old cabinets and the wall.
PHASE 3: BEAM AND FRAMING
☐ 5. Install temporary supports.
☐ 6. Set the new beam and posts.
PHASE 4: ROUGH ELECTRICAL AND PLUMBING
☐ 7. Move the sink line.
☐ 8. Add under-cabinet lighting circuits.
PHASE 5: CABINETS AND COUNTERS
☐ 9. Hang wall and base cabinets.
☐ 10. Install butcher-block counters and shelves.
PHASE 6: FINISH AND WALKTHROUGH
☐ 11. Paint, trim and touch-up.
☐ 12. Walk through the finished kitchen with the client.
When to tell Nick to invoice
| 1 | At acceptance of the estimate |
| 2 | Upon completion of Phases 1–2, Steps 1–4 |
| 3 | Upon completion of Phases 3–4, Steps 5–8 |
| 4 | Upon completion of Phase 5, Steps 9–10 |
| 5 | Upon completion of Phase 6, Steps 11–12 |
Anything the client asks for that isn't in the steps above is a change order: write it down, tell Nick, and wait for the signed change before doing it.