SCOPE OF WORK / ESTIMATE

Version 1 – 10/21/26 · Job 1002-CHE

PROJECT

Replace the tub with a walk-in tile shower and glass door, new vanity, fan and lighting.

LABOR

PHASE 1 — DEMOLITION

  1. 1. Remove tub, tile and vanity.
  2. 2. Check the subfloor.

PHASE 2 — PLUMBING AND WATERPROOFING

  1. 3. Move the drain for the shower.
  2. 4. Install the waterproof membrane.

PHASE 3 — TILE

  1. 5. Set floor and wall tile.
  2. 6. Grout and seal.

PHASE 4 — FIXTURES

  1. 7. Install vanity, faucet and shower valve trim.
  2. 8. Hang the glass door.

PHASE 5 — FINAL CHECK

  1. 9. Test the fan and water.
  2. 10. Walk through with the client.

SCHEDULE / CREW

Business days on site: 12-15 days on site.
Crew: 1 general contractor, 1 tile setter

FEES

LABOR$9,800.00
MATERIALS$8,000.00
DEBRIS DISPOSAL / DUMP FEES$600.00
TOTAL FEES$18,400.00

PAYMENT SCHEDULE

PaymentForDueAmount
1002-CHE-1Schedule hold + all materials + 25% of laborAt acceptance of the estimate$10,450.00
1002-CHE-225% of labor: Phases 1–2Upon completion of Phases 1–2, Steps 1–4$2,450.00
1002-CHE-325% of labor: Phase 3Upon completion of Phase 3, Steps 5–6$2,450.00
1002-CHE-425% of labor: Phases 4–5 + debris / dump feeUpon completion of Phases 4–5, Steps 7–10$3,050.00
Changes to this scope or price require a written, signed Change Order.