SCOPE OF WORK / ESTIMATE
Version 1 – 10/21/26 · Job 1002-CHE
PROJECT
Replace the tub with a walk-in tile shower and glass door, new vanity, fan and lighting.
LABOR
PHASE 1 — DEMOLITION
- 1. Remove tub, tile and vanity.
- 2. Check the subfloor.
PHASE 2 — PLUMBING AND WATERPROOFING
- 3. Move the drain for the shower.
- 4. Install the waterproof membrane.
PHASE 3 — TILE
- 5. Set floor and wall tile.
- 6. Grout and seal.
PHASE 4 — FIXTURES
- 7. Install vanity, faucet and shower valve trim.
- 8. Hang the glass door.
PHASE 5 — FINAL CHECK
- 9. Test the fan and water.
- 10. Walk through with the client.
SCHEDULE / CREW
Business days on site: 12-15 days on site.
Crew: 1 general contractor, 1 tile setter
FEES
| LABOR | $9,800.00 |
| MATERIALS | $8,000.00 |
| DEBRIS DISPOSAL / DUMP FEES | $600.00 |
| TOTAL FEES | $18,400.00 |
PAYMENT SCHEDULE
| Payment | For | Due | Amount |
| 1002-CHE-1 | Schedule hold + all materials + 25% of labor | At acceptance of the estimate | $10,450.00 |
| 1002-CHE-2 | 25% of labor: Phases 1–2 | Upon completion of Phases 1–2, Steps 1–4 | $2,450.00 |
| 1002-CHE-3 | 25% of labor: Phase 3 | Upon completion of Phase 3, Steps 5–6 | $2,450.00 |
| 1002-CHE-4 | 25% of labor: Phases 4–5 + debris / dump fee | Upon completion of Phases 4–5, Steps 7–10 | $3,050.00 |
Changes to this scope or price require a written, signed Change Order.