PROJECT

Remove the wall between kitchen and dining room, add a beam, new cabinets, butcher-block counters and open shelves.

LABOR

PHASE 1 — LAYOUT AND ORDERING

  1. 1. Measure and confirm the cabinet layout.
  2. 2. Order cabinets and counters.

PHASE 2 — PROTECTION AND DEMOLITION

  1. 3. Protect floors and doorways.
  2. 4. Remove old cabinets and the wall.

PHASE 3 — BEAM AND FRAMING

  1. 5. Install temporary supports.
  2. 6. Set the new beam and posts.

PHASE 4 — ROUGH ELECTRICAL AND PLUMBING

  1. 7. Move the sink line.
  2. 8. Add under-cabinet lighting circuits.

PHASE 5 — CABINETS AND COUNTERS

  1. 9. Hang wall and base cabinets.
  2. 10. Install butcher-block counters and shelves.

PHASE 6 — FINISH AND WALKTHROUGH

  1. 11. Paint, trim and touch-up.
  2. 12. Walk through the finished kitchen with the client.

SCHEDULE / CREW

Business days on site: 4-5 weeks on site, Monday-Friday.
Crew: 1 general contractor, 1 carpenter, 1 helper part-time

FEES

LABOR$16,800.00
MATERIALS$17,750.00
DEBRIS DISPOSAL / DUMP FEES$900.00
TOTAL FEES$35,450.00

PAYMENT SCHEDULE

PaymentForDueAmount
1001-ALV-1Schedule hold + all materials + 20% of laborAt acceptance of the estimate$21,110.00
1001-ALV-220% of labor: Phases 1–2Upon completion of Phases 1–2, Steps 1–4$3,360.00
1001-ALV-320% of labor: Phases 3–4Upon completion of Phases 3–4, Steps 5–8$3,360.00
1001-ALV-420% of labor: Phase 5Upon completion of Phase 5, Steps 9–10$3,360.00
1001-ALV-520% of labor: Phase 6 + debris / dump feeUpon completion of Phase 6, Steps 11–12$4,260.00
Changes to this scope or price require a written, signed Change Order.