Reclaimed Space Crafters
4 Briar Lane, Saratoga Springs, NY 12866 • owner@example.com • 518-932-9919
Dana Alvarez
14 Sample Lane, Saratoga Springs, NY
SCOPE OF WORK / ESTIMATE
Version 1 – 10/21/26 · Job 1001-ALV
PROJECT
Remove the wall between kitchen and dining room, add a beam, new cabinets, butcher-block counters and open shelves.
LABOR
PHASE 1 — LAYOUT AND ORDERING
- 1. Measure and confirm the cabinet layout.
- 2. Order cabinets and counters.
PHASE 2 — PROTECTION AND DEMOLITION
- 3. Protect floors and doorways.
- 4. Remove old cabinets and the wall.
PHASE 3 — BEAM AND FRAMING
- 5. Install temporary supports.
- 6. Set the new beam and posts.
PHASE 4 — ROUGH ELECTRICAL AND PLUMBING
- 7. Move the sink line.
- 8. Add under-cabinet lighting circuits.
PHASE 5 — CABINETS AND COUNTERS
- 9. Hang wall and base cabinets.
- 10. Install butcher-block counters and shelves.
PHASE 6 — FINISH AND WALKTHROUGH
- 11. Paint, trim and touch-up.
- 12. Walk through the finished kitchen with the client.
SCHEDULE / CREW
Business days on site: 4-5 weeks on site, Monday-Friday.
Crew: 1 general contractor, 1 carpenter, 1 helper part-time
FEES
| LABOR | $16,800.00 |
| MATERIALS | $17,750.00 |
| DEBRIS DISPOSAL / DUMP FEES | $900.00 |
| TOTAL FEES | $35,450.00 |
PAYMENT SCHEDULE
| Payment | For | Due | Amount |
| 1001-ALV-1 | Schedule hold + all materials + 20% of labor | At acceptance of the estimate | $21,110.00 |
| 1001-ALV-2 | 20% of labor: Phases 1–2 | Upon completion of Phases 1–2, Steps 1–4 | $3,360.00 |
| 1001-ALV-3 | 20% of labor: Phases 3–4 | Upon completion of Phases 3–4, Steps 5–8 | $3,360.00 |
| 1001-ALV-4 | 20% of labor: Phase 5 | Upon completion of Phase 5, Steps 9–10 | $3,360.00 |
| 1001-ALV-5 | 20% of labor: Phase 6 + debris / dump fee | Upon completion of Phase 6, Steps 11–12 | $4,260.00 |
Changes to this scope or price require a written, signed Change Order.