Crew brief · 1003-BRO

Jordan Brooks · 88 Demo Road, Malta, NY · 555-0100
Deck / Exterior · 8-10 days on site, weather permitting. · Crew: 1 general contractor, 1 helper · about 144 crew-hours

Replace the rear deck and stairs with pressure-treated framing, composite decking and a new rail.

Before you start

Work, step by step

PHASE 1: DEMOLITION

☐ 1. Remove old decking, rail and stairs.

PHASE 2: FOOTINGS AND FRAMING

☐ 2. Set piers and frame the deck.

PHASE 3: DECKING AND STAIRS

☐ 3. Install composite boards and stairs.

PHASE 4: RAIL AND CLEANUP

☐ 4. Install the rail.
☐ 5. Haul debris.

When to tell Nick to invoice

1At acceptance of the estimate
2Upon completion of Phases 1–2, Steps 1–2
3Upon completion of Phase 3, Step 3
4Upon completion of Phase 4, Steps 4–5

Anything the client asks for that isn't in the steps above is a change order: write it down, tell Nick, and wait for the signed change before doing it.