Crew brief · 1002-CHE
Sam Chen · 3 Example Court, Wilton, NY · 555-0100
Bathroom · 12-15 days on site. · Crew: 1 general contractor, 1 tile setter · about 216 crew-hours
Replace the tub with a walk-in tile shower and glass door, new vanity, fan and lighting.
Before you start
- First payment received and materials ordered. Call Nick if not.
- Photos of the work area before you touch anything.
- Any subcontractor on site has a current insurance certificate.
- Daily: who worked and how many hours goes into the Crew tab.
Work, step by step
PHASE 1: DEMOLITION
☐ 1. Remove tub, tile and vanity.
☐ 2. Check the subfloor.
PHASE 2: PLUMBING AND WATERPROOFING
☐ 3. Move the drain for the shower.
☐ 4. Install the waterproof membrane.
PHASE 3: TILE
☐ 5. Set floor and wall tile.
☐ 6. Grout and seal.
PHASE 4: FIXTURES
☐ 7. Install vanity, faucet and shower valve trim.
☐ 8. Hang the glass door.
PHASE 5: FINAL CHECK
☐ 9. Test the fan and water.
☐ 10. Walk through with the client.
When to tell Nick to invoice
| 1 | At acceptance of the estimate |
| 2 | Upon completion of Phases 1–2, Steps 1–4 |
| 3 | Upon completion of Phase 3, Steps 5–6 |
| 4 | Upon completion of Phases 4–5, Steps 7–10 |
Anything the client asks for that isn't in the steps above is a change order: write it down, tell Nick, and wait for the signed change before doing it.