Sam Chen · 3 Example Court, Wilton, NY · 555-0100
Bathroom · 12-15 days on site. · Crew: 1 general contractor, 1 tile setter · about 216 crew-hours

Replace the tub with a walk-in tile shower and glass door, new vanity, fan and lighting.

Before you start

Work, step by step

PHASE 1: DEMOLITION

☐ 1. Remove tub, tile and vanity.
☐ 2. Check the subfloor.

PHASE 2: PLUMBING AND WATERPROOFING

☐ 3. Move the drain for the shower.
☐ 4. Install the waterproof membrane.

PHASE 3: TILE

☐ 5. Set floor and wall tile.
☐ 6. Grout and seal.

PHASE 4: FIXTURES

☐ 7. Install vanity, faucet and shower valve trim.
☐ 8. Hang the glass door.

PHASE 5: FINAL CHECK

☐ 9. Test the fan and water.
☐ 10. Walk through with the client.

When to tell Nick to invoice

1At acceptance of the estimate
2Upon completion of Phases 1–2, Steps 1–4
3Upon completion of Phase 3, Steps 5–6
4Upon completion of Phases 4–5, Steps 7–10

Anything the client asks for that isn't in the steps above is a change order: write it down, tell Nick, and wait for the signed change before doing it.